English हिन्दी
Connect with us

India News

CAG audit report on Army for 2021 tabled in Parliament

Published

on

The Comptroller and Auditor General’s Audit Report no. 11 of 2024 Union Government (Defence Services – Army) for the year ended March 2021 was laid in the Parliament today.

The report contains the results of audit of the transactions of Ministry of Defence pertaining to Department of Defence, Army, Military Engineer Services, Border Roads Organisation, and Defence Research and Development Organisation in 2020-21.

Some significant audit findings are

Functioning of the Remount and Veterinary Services and Utilisation of Animal Transport Units: The Remount and Veterinary Corps (RVC), headed by Director General Remount Veterinary Services (DG RVS), is responsible for breeding, rearing, training and managing health of the entire equine and canine population in the Indian Army.


Audit covered the period from 2018-19 to 2020-21 which included the period of 13th Army Plan (2017-22). Audit observed that the 13th Plan for RVS did not include capability development and modernisation aspects. Further, three out of the six short-term training goals as per the Technical Training Directive of RVS, related to import of frozen semen of proven elite stallions from European Countries to upgrade the sporting potential of Army Equines; training of raptors to hunt down drones/surveillance devices; and training of local breeds of dogs to assess their suitability for employment as military working dogs, were either not achieved or under-achieved. It was further observed that in four out of five selected Animal Transport Units, the distance between the Animal Transport Units (ATs) and the dependent deployment ranged between 174 kilometres and 534 kilometres resulting in extra expenditure on transportation of mules and under-utilisation of ATs ranging between 89.46 per cent and 10.74 per cent. The revision of old Veterinary Mobilisation Equipment Scales was held up at DG RVS/ Director General Armed Forces Medical Services for more than 16 years. As a result, the scales which were in use were devoid of the latest technological developments in the field of veterinary medicine.

Wasteful expenditure due to poor management of hired office accommodation: The office of the Chief Administrative Officer (CAO) under the Ministry of Defence, on grounds of safety concerns involved in the existing old hutment buildings, hired office accommodation measuring 45,278.31 square feet in November/December 2018, for housing the defence offices that occupied these hutments. As of March 2023, only 42 per cent of the total hired space was utilised and balance 58 per cent of hired space remained unutilised since its hiring. Moreover, the hired office space was not actually utilised by the intended users for whom the office space was hired.


Poor management of hired office space by the CAO coupled with the inability of the designated defence users to shift to the said premises for a period of more than four years resulted in wasteful expenditure of ₹44.26 crore (March 2023) on account of rent of the unutilised space as well as renovation works carried out therein.


Raising of Porter Companies in Eastern Command: Ministry of Defence sanctioned (June 2019) raising of nine Porter Companies (Coys) in the area of responsibility (AoR) under the Headquarters Eastern Command (HQ EC) for the years 2019-20 and 2020-21 at a cost of ₹180.85 crore and for the year 2021-22, at a cost of ₹93.78 crore.


The assessment of requirement of porters carried out by the two Division HQ (HQ ‘C1’ Division and HQ ‘C2’ Division), under HQ ‘C’ Corps, was not commensurate with their respective five- year Roll-on Plans (RoPs). The Engineer Task Forces (ETFs) under these Divisions were marginally short of manpower for the years 2019-20 and 2020-21 and had surplus manpower during the financial year 2021-22 for the execution of operational works as per the RoPs. However, the Ministry, on the basis of projection of requirements, sanctioned eight Porter Coys for the period from 2019-20 to 2021-22 comprising 600 porters in each Porter Coy for HQ ‘C’ Corps.


The works projected by three Corps HQ for obtaining sanction for raising of Porter Coys were in excess of works actually executed during 2019-20 to 2021-22 to the extent of 41 to 499 per cent. Two Corps HQ (HQ ‘A’ Corps and HQ ‘C’ Corps) projected 8,635 porters, involving an expenditure amounting to ₹112.93 crore, in excess of the requirement based on the volume of works executed during the years 2019-20 to 2021-22.


The sanction for raising of Porter Coys for the years 2020-21 and 2021-22 was issued in time by the Ministry. However, HQ ‘B’ Corps and HQ ‘C’ Corps raised Porter Coys with a delay of up to three months. The delay in the raising of Porter Coys contributed to fall in the strength of porters in seven out of eight selected Porter Coys due to onset of winter.
Out of total 12,000 porters hired under the Porter Coys raised between 2019-20 and 2021-22, Corps HQ allotted 11,297 porters to ETFs/Engineer Regiments. Division HQ further allotted only 7,938 porters to ETFs/Engineer Regiments. As such, 3,359 porters were deployed in units other than Engineer Regiments. Out of 7,938 porters deployed, the utilisation certificates rendered by the Engineer Regiments were only in respect of 4,634 porters.

There was an overpayment of ₹2.53 crore to Porters due to payment of salary on a daily basis instead of on monthly basis and payment at enhanced rates of basic pay and dearness allowance to Porters deployed as mates. Besides, ₹1.21 crore were also paid on account of high altitude allowance (HAA) to those porters who were not deployed in high altitude areas. There was delay in disbursement of salary to porters ranging from one to five months.
There was shortfall of 97and 80 per cent in respect of HQ ‘A’ Corps and HQ ‘B’ Corps in construction of Permanent Defences (PDs) against those projected in the five-year RoP (2018-23), despite sanctioning of Porter Coys during 2019-20 to 2021-22. Audit found that in respect of two Corps HQ, no Board of Officers (BOO) was held for handing over the assets to the users during the years 2020-21 and 2021-22 (HQ ‘A’ Corps), and 2021-22 (HQ ‘C’ Corps). In HQ ‘C’ Corps (HQ ‘C2’ Div.) for the years 2019-20 and 2020-21, Numerical Asset Register (NAR) was not updated and there was a mismatch between the number of PDs, shelters and storage accommodation constructed, and those reflected in the NAR.


Court of Inquiry in Indian Army:


There were persistent delays in finalisation of the CoI proceedings in Indian Army. Out of 95 cases involving financial loss in the three Army Commands (Central Command, Eastern Command and Western Command), stipulated timeline for assembly and completion of CoI was met only in 46 and 25 cases respectively. In 11 cases, time taken in completion of CoI was more than two years and even up to 11 years. In 10 CoIs related to fire incidents where the Command HQs were authorised to convene a CoI, the convening order was issued by an authority lower than the Command HQs. The terms of reference (ToR) which lay down the scope of investigation for a CoI did not have specific mention of fixation of responsibility and apportioning of blame/loss in 29 cases. Further, in 28 out of these 29 cases, there was no mention of the relevant Army Rules, Orders, Instructions, etc., and in 13 of these 29 cases, no mention was made of assessing the extent of loss and damage to life/property.


In 95 cases, CoI assessed financial loss of ₹50.76 crore. The financial losses of ₹7.12 crore were regularised in respect of 43 cases (April 2022). However, in 52 cases involving financial loss of 43.64 crore, the information relating to regularisation of loss by Competent Financial Authority was not available. In 57 out of 95 cases, the required documents relating to intimation of details of loss to accounting authorities, that is, Controllers of Defence Accounts (CsDA), were not available in the documents furnished. As such, Audit was unable to ascertain whether the loss was reported to CsDA either initially or finally after investigation. In 20 out of 38 remaining cases, where the Commands/Units furnished details of financial losses to the concerned CsDA after completion of CoI, the time taken in reporting of losses to CsDA ranged between three months and more than two years.


Hiring of accommodation due to inordinate delay in construction of warehouse: Lackadaisical approach on the part of authorities of the Canteen Stores Department (CSD) and the Military Engineer Services (MES) in processing the case for construction of a warehouse for CSD Area Depot Chennai, first initiated in February 2011, coupled with delay on

the part of Ministry of Defence (Ministry) in according sanction, resulted in inordinate delay of 393 weeks in pre-administrative approval planning. The overall time taken in processing the proposal and according the sanction was 441 weeks as against the stipulated time frame of 48 weeks. There were further delays even after the work was sanctioned in July 2019 due to late release of funds by the Ministry. The contract was finally concluded in December 2022 and the work is scheduled to be completed by November 2024. CSD has paid ₹17.43 crore as rent from October 2018 to December 2022 towards hiring of a warehouse for the CSD Area Depot Chennai.


Unwarranted expenditure due to delay in termination of Bandwidth services by the Canteen Stores Department: The VSAT connectivity required for functioning of the Integrated Canteen Stores Department (ICSD) system, was unsatisfactory since October 2009 which was well known to the CSD. The letter for termination of VSAT services was issued only in July 2014, though the payments towards VSAT connections were stopped by the CSD since October 2013. Meanwhile, as the contract remained in force from October 2013 to June 2014, the firm raised invoices for VSAT Services indicating that 18 per cent interest would be charged on delayed payment, which was not responded to by the CSD.


The firm filed (July 2017) a suit in the Delhi High Court which appointed (August 2018) a Sole Arbitrator for the case. The Arbitral award was pronounced (February 2020) in favour of the claimant and CSD had to incur an unwarranted expenditure of ₹1.85 crore towards arbitration award.


Avoidable extra expenditure due to acceptance of unreasonable rate: Integrated Headquarters of Ministry of Defence (IHQ) (Army) floated (January 2018) an open tender enquiry for the supply of 8,831 pieces of ‘S’ item. Only M/s Ashok Leyland, the Original Equipment Manufacturer (OEM), qualified in the technical bids. OEM quoted (May 2018) a base price of
₹4,500 (exclusive of tax). Director General of Ordnance Services (DGOS) at the Army HQ placed (August 2018) the Supply Order (SO) after a gap of three months as against the prescribed four weeks.


In the interregnum, Central Ordnance Depot (COD), Dehu Road, separately placed a SO (July 2018) for procurement of 1,617 pieces of the ibid item at a base price of ₹8,400 (exclusive of tax) through a limited tender issued (June 2018) to 14 shortlisted suppliers (excluding the OEM). This rate was much higher than the Army HQ determined price of May 2018 by ₹3,900 per piece (excluding tax). While assessing the reasonableness of the cost, COD compared the rates with its earlier procurement (February 2016) from the same vendor which was ₹8,400 (excluding tax) instead of comparing it with its last procurement (September 2017) from OEM which was ₹4,551 (excluding tax).


This resulted in COD, Dehu Road procuring the item in July 2018 at a price higher than the price at which Army HQ had finalized contract for the same item in May 2018, thus incurring an avoidable extra expenditure of ₹80.72 lakh inclusive of tax.

Management of Water Supply by Military Engineer Services: Military Engineer Services (MES) is responsible for the erection, operation and maintenance of all defence services installations for the supply of water to users in its assigned area of responsibility viz. Military stations, Cantonment Boards and other Defence Installations.


Audit examination of records for the period from 2018-19 to 2020-21 at 20 selected Garrison Engineers (GEs), under six commands, regarding management and augmentation of water supply revealed that in 15 out of 20 GEs selected, water supplied to the users was less than that authorised. The less supply of water in the said 15 GEs ranged from 10.13 per cent to 62.97 per cent of the authorised quantity.


To reduce the gap between the demand and supply of water in their respective service areas, 13 GEs had signed Memoranda of Understanding/agreements with outside agencies (water supply utilities). Analysis of the information on actual water supply by the contracted agencies revealed that 12 out of the 13 GEs were receiving less than the agreed upon quantity of water from these agencies.


Engineer-in-Chief’s Branch had issued (November 2018) instructions to implement the automation of process supervisory management of water supply system within the MES. This had not been implemented by16 GEs.


It was further observed that 14,940.33 lakh gallons of water were lost due to leakage in the period from 2018-19 to 2020-21. The total loss on account of leakage of water calculated on the basis of ‘All-in-Cost’ worked out to ₹11.53 crore.


Out of 10 projects related to augmentation of water supply under Annual Major Works Programme (AMWP), which were selected for detailed audit, only four projects were completed whereas one project had yet not started and five projects, which had started, were still to be completed.


Significant lapses such as non-compliance with applicable standards of the Bureau of Indian Standards (BIS) for quality of drinking water, non-cleaning of Overhead Tanks/Reservoirs at the prescribed frequency, and non-functional equipment for water decontamination were noticed.


There was less allotment of funds against demand in the water supply maintenance head during the years 2018-19 to 2020-21 in 18 of the selected GEs ranging from 13.80 per cent to 47.67 per cent.


Irregular payment of Electricity Duty by MES formations due to failure to install separate meters for domestic and non-domestic consumption of electricity: Military Engineer Service is responsible for the management of electric supply in all the military stations/cantonment areas in the country, for which it receives bulk electric supply from the State Electricity Boards or companies (supplying agencies). Before payment to the supply agency for bulk supply of electricity as per the applicable charges, Garrison Engineer (GE) concerned is required to enforce pre-checks on the bills. Audit observed that despite the assurance given by the Ministry, GE, Mhow and GE, Jabalpur paid Electricity Duty (ED) amounting to ₹4.81 crore

(March 2022) on non-domestic (non-dutiable) consumption of electricity by Defence Establishments to electricity supplying agencies. Non-recovery of allied electricity charges on domestic supply by Garrison Engineer (Faridkot) amounting to ₹1.28 crore: An amount of ₹ 1.28 crore remained unrecovered for the period of 2018-19 to 2020-21 from domestic users residing in Faridkot military station due to failure of Garrison Engineer Faridkot to ensure recovery of electricity charges as per stipulated regulations.


Avoidable expenditure of ₹3.20 crore on account of not following the IRC specification in road markings: Chief Engineer (Project) Chetak failed to incorporate IRC standards in the 38 contracts related to road resurfacing concluded during the period 2019-20 to 2021-22 and provide edge line marking of width 150mm instead 100 mm resulting in avoidable expenditure of ₹ 3.20 crore on account of laying of thermoplastic paint on the excess area.


Sanctioning similar nature of works under different code heads: Defence Research & Development Laboratory (DRDL), Hyderabad sanctioned ₹4.10 crore for procurement of a Closed Circuit Television (CCTV) surveillance system for the entire perimeter wall of the lab exercising the financial powers delegated to the Director under Sl. No. 2.2 of Delegation of Financial Powers, 2019 (DFP). The said delegation is applicable only for procurement of scientific equipment and material for labs/workshops. Intent of DFP is to consider only that equipment as scientific equipment which may be required in connection with the scientific research and development work pertaining to the laboratory. As such, installation of CCTV surveillance system should come under the ambit of ‘Works’ and not ‘Procurement of scientific equipment’. Incidentally, based on the requirement of CCTV surveillance cameras projected by another laboratory, Director, Civil Works & Estates, Head of the Construction Wing of Defence Research and Development Organisation (DRDO), had accorded required sanction under Sl. No. 4.1 of DFP, which is applicable for ‘Works’.


Avoidable expenditure of ₹2.78 crore: Injudicious selection of location for setting up of the Defence Research & Development Organisation Young Scientist Laboratory – Asymmetric Warfare Technologies (DYSL-AT) at Kolkata resulted in relocation of the Laboratory within one year and four months to Hyderabad. During this period, an expenditure of ₹2.78 crore was incurred on civil works/rent at two different sites towards establishment of DYSL-AT at Kolkata which was avoidable.

Continue Reading

India News

Massive fire destroys around 80 shanties in west Delhi, hundreds left homeless

A massive blaze swept through a slum cluster in west Delhi’s Matiala village, destroying around 80 shanties and leaving hundreds of migrant families homeless overnight.

Published

on

massive fire

A massive overnight fire destroyed around 80 shanties in west Delhi, leaving hundreds of migrant families homeless after flames swept through a large slum settlement near Uttam Nagar.

The incident took place late on the night of March 11 at the Machhli Mandi shanty cluster in Matiala village. The blaze spread rapidly across nearly four acres, reducing homes made of bamboo, tarpaulin and plastic sheets to ashes within hours.

According to Delhi Police, the affected families were largely migrant workers from Bihar who earn their livelihood as daily-wage labourers and ragpickers. Though no deaths were reported, residents lost most of their belongings including clothes, utensils, food supplies and documents.

Firefighters battle flames through the night

The Delhi Fire Service deployed 23 fire tenders to control the blaze. Firefighters continued operations throughout the night and managed to bring the flames under control at around 3 am on Thursday. Cooling operations continued afterward to prevent the fire from reigniting.

Thick grey ash and burnt debris covered large parts of the area after the fire. Charred bamboo frames, melted plastic sheets and twisted tin roofs were scattered across the ground.

Some residents claimed they saw unidentified people arrive on motorcycles and set several huts on fire before fleeing. Authorities have not confirmed this allegation.

Authorities cite disputed land and possible waste burning

District Magistrate Mekala Chaitanya visited the site and said the land has been under dispute for a long time.

He stated that the occupants had been issued an evacuation notice on March 7, with the night of the fire marking the final deadline to vacate the area.

An investigation is underway to determine the exact cause of the fire. The district administration suggested that the blaze may have started due to ragpickers burning waste at night, a practice commonly reported in the area.

Officials also noted that a similar fire incident had occurred earlier this month at the same location after illegal garbage dumping, which required eight fire tenders to extinguish.

Police say evacuation prevented casualties

Deputy Commissioner of Police (Dwarka) Kushal Pal Singh said police teams helped evacuate residents before the fire intensified.

He said the temporary structures were made from highly flammable materials, which allowed the fire to spread quickly. However, swift action by police and firefighters ensured that no lives were lost.

Families struggle after losing everything

Residents said they are now struggling to survive without basic necessities.

Rani Devi, a mother of three, said her family had no food, milk or drinking water after the fire destroyed their home and belongings. She added that many families were now sleeping amid the burnt debris.

A student, Rahul Kumar, whose board examinations are scheduled to begin soon, said his textbooks, notebooks and school uniform were all destroyed in the blaze.

Another resident, 42-year-old Rajesh Paswan, who migrated from Bihar over a decade ago and works as a ragpicker, said the fire wiped out everything his family owned overnight.

Demand for compensation and rehabilitation

AAP leader Ramesh Matitala met affected families and called for immediate compensation and rehabilitation.

He said the families should be provided financial assistance and relocated to a safer place, adding that authorities must ensure accountability if negligence or foul play is found in the investigation.

Continue Reading

India News

Mamata Banerjee questions PM Modi’s respect for President Murmu using 2024 photograph

Mamata Banerjee criticised Prime Minister Narendra Modi using a 2024 photograph during a rally as political tensions grow over President Droupadi Murmu’s visit to West Bengal.

Published

on

mamta banerjee

West Bengal Chief Minister Mamata Banerjee has intensified her attack on Prime Minister Narendra Modi amid a growing dispute over President Droupadi Murmu’s recent visit to the state.

Speaking at a public rally, Banerjee referred to a photograph from March 2024 that shows the President standing while the Prime Minister is seated during a meeting with veteran leader Lal Krishna Advani. The Trinamool Congress leader questioned the government’s claims about respecting the office of the President.

According to a video shared by the Trinamool Congress, two party leaders displayed the photograph while Banerjee addressed the gathering. She argued that while leaders often speak about honouring the President’s office, such visual moments raise questions about whether that respect is truly reflected in conduct.

The photograph referenced by Banerjee was taken on March 31, 2024, when President Murmu and Prime Minister Modi visited Advani to present him with the Bharat Ratna.

Banerjee said the image showed the President standing while the Prime Minister remained seated. She asked whether the government truly respected the country’s first tribal woman President, adding that the picture demonstrated “who respects and who does not”.

President’s visit to Bengal triggers controversy

The political exchange began after President Murmu visited West Bengal on Saturday to attend the ninth International Santal Conference in Darjeeling.

While addressing the event, the President publicly noted that neither the chief minister nor other state ministers were present to receive her. She said that usually the chief minister welcomes the President during such visits but that did not happen in this case.

Murmu added that Banerjee is like a “younger sister” to her and said she did not know whether the chief minister was upset.

The President also raised concerns about the change in the event venue and suggested that the new location made it difficult for people to attend. She said she did not know why the state administration had not permitted the programme at the earlier venue.

Prime minister criticises Bengal government

Reacting to the developments, Prime Minister Modi described the situation as “shameful and unprecedented”. In a post on social media, he said the incident had saddened people who believe in democracy and in empowering tribal communities.

He added that the pain expressed by President Murmu had caused widespread concern and accused the West Bengal government of disrespecting the office of the President. The Prime Minister also said the dignity of the President’s position should remain above political disputes.

Speaking at a public event later, Modi said the developments were particularly unfortunate as they occurred on International Women’s Day. He alleged that the Trinamool Congress government had boycotted both the tribal event and the President.

Mamata Banerjee denies protocol violation

Banerjee rejected the allegations, saying no protocol lapse occurred during the visit.

According to the chief minister, the event had been organised by a private body, the International Santal Council, which invited the President to attend the conference in Siliguri. She said the district administration had warned the President’s Secretariat that the organisers lacked adequate arrangements to host such a programme.

Banerjee also stated that the advance team from the President’s Secretariat visited the site earlier in March and was informed about the shortcomings but the event continued as scheduled.

She added that officials including the mayor of Siliguri Municipal Corporation, the Darjeeling district magistrate and the Siliguri police commissioner received and saw off the President according to the approved protocol lineup.

The chief minister said she was not part of the official lineup or the event’s dais plan and accused the BJP of using the country’s highest constitutional office for political purposes.

Centre seeks report from state

The issue escalated further after Union Home Secretary Govind Mohan wrote to West Bengal Chief Secretary Nandini Chakravorty seeking a report on alleged lapses during the President’s visit.

According to sources, the letter asked why senior state officials such as the chief minister, the chief secretary and the director general of police were not present to receive the President. It also raised concerns about reports of poor arrangements at the venue, including the absence of water in a washroom designated for the President and garbage along the route.

Officials from the Darjeeling district administration and Siliguri police were also mentioned in the communication, with the Centre seeking details of any action taken.

The controversy has now turned into a sharp political confrontation between the Centre and the West Bengal government.

Continue Reading

India News

President Murmu questions tribal development in Bengal, Mamata Banerjee calls remarks political

President Droupadi Murmu raised concerns about tribal development in West Bengal and questioned the absence of state representatives during her north Bengal visit. Mamata Banerjee called the remarks political and said they were based on misinformation.

Published

on

mamta banerjee

President Droupadi Murmu on Saturday raised questions about the development of tribal communities in West Bengal and also expressed surprise over the absence of state government representatives during her visit to north Bengal.

Speaking at the International Santhal Conference, an event organised for the tribal community, the President wondered whether Chief Minister Mamata Banerjee was upset with her, as neither the chief minister nor any minister from the state cabinet was present to receive her.

Murmu also referred to the decision to shift the venue of the conference from Bidhannagar to Goshaipur. She questioned why the programme was not allowed at the earlier venue despite adequate space being available.

Addressing the gathering, the President said she did not know whether Banerjee was upset with her and remarked that she also considers herself a daughter of Bengal. She added that Banerjee was like a younger sister to her but the reason behind shifting the programme location remained unclear.

During her speech, Murmu also raised broader concerns about the condition of tribal communities in the region. She questioned whether development and facilities intended for Santhals and other tribal groups were actually reaching them.

According to the President, the Centre has worked over the past decade to strengthen tribal identity and accelerate development for tribal communities. However, she said it did not appear that the benefits were reaching people in the region.

Murmu also suggested that some individuals might have been prevented from attending the event and said it appeared that certain groups did not want the Santhal community to unite, progress, or gain access to education and strength.

The remarks triggered a political response, with Prime Minister Narendra Modi criticising the situation. Sharing a video of the President’s speech, he said the incident was shameful and expressed concern over what he described as an insult to the President and to Santhal culture.

The BJP also criticised the West Bengal government, alleging that the lack of preparation and protocol during the President’s visit reflected administrative failure and disrespect for constitutional offices.

Responding to the President’s remarks, Mamata Banerjee said the statements were political in nature. Speaking during a protest in Kolkata against the Special Intensive Revision of voter rolls, the chief minister urged the President to avoid making remarks that could affect the dignity of the office.

Banerjee said the President had spoken about only one community and not about others in the state. She also asked her party’s MPs to seek an appointment with Rashtrapati Bhavan to present details of the state government’s work for Scheduled Tribe and Scheduled Caste communities.

The Trinamool Congress also rejected the suggestion that there had been no development for tribal communities in the state. In a statement, the party said the President appeared to have been misinformed.

The party highlighted several welfare initiatives, including financial assistance under the Lakshmir Bhandar scheme. It said women from Scheduled Tribe communities now receive Rs 1,700 per month, amounting to Rs 20,400 annually.

The Trinamool Congress also referred to scholarships for tribal students, the establishment of schools and other development programmes aimed at improving conditions in tribal areas.

According to the party, these measures represent concrete initiatives designed to improve opportunities, dignity and development for Adivasi communities across West Bengal.

Continue Reading

Trending

© Copyright 2022 APNLIVE.com