English हिन्दी
Connect with us

India News

CAG audit report on Army for 2021 tabled in Parliament

Published

on

The Comptroller and Auditor General’s Audit Report no. 11 of 2024 Union Government (Defence Services – Army) for the year ended March 2021 was laid in the Parliament today.

The report contains the results of audit of the transactions of Ministry of Defence pertaining to Department of Defence, Army, Military Engineer Services, Border Roads Organisation, and Defence Research and Development Organisation in 2020-21.

Some significant audit findings are

Functioning of the Remount and Veterinary Services and Utilisation of Animal Transport Units: The Remount and Veterinary Corps (RVC), headed by Director General Remount Veterinary Services (DG RVS), is responsible for breeding, rearing, training and managing health of the entire equine and canine population in the Indian Army.


Audit covered the period from 2018-19 to 2020-21 which included the period of 13th Army Plan (2017-22). Audit observed that the 13th Plan for RVS did not include capability development and modernisation aspects. Further, three out of the six short-term training goals as per the Technical Training Directive of RVS, related to import of frozen semen of proven elite stallions from European Countries to upgrade the sporting potential of Army Equines; training of raptors to hunt down drones/surveillance devices; and training of local breeds of dogs to assess their suitability for employment as military working dogs, were either not achieved or under-achieved. It was further observed that in four out of five selected Animal Transport Units, the distance between the Animal Transport Units (ATs) and the dependent deployment ranged between 174 kilometres and 534 kilometres resulting in extra expenditure on transportation of mules and under-utilisation of ATs ranging between 89.46 per cent and 10.74 per cent. The revision of old Veterinary Mobilisation Equipment Scales was held up at DG RVS/ Director General Armed Forces Medical Services for more than 16 years. As a result, the scales which were in use were devoid of the latest technological developments in the field of veterinary medicine.

Wasteful expenditure due to poor management of hired office accommodation: The office of the Chief Administrative Officer (CAO) under the Ministry of Defence, on grounds of safety concerns involved in the existing old hutment buildings, hired office accommodation measuring 45,278.31 square feet in November/December 2018, for housing the defence offices that occupied these hutments. As of March 2023, only 42 per cent of the total hired space was utilised and balance 58 per cent of hired space remained unutilised since its hiring. Moreover, the hired office space was not actually utilised by the intended users for whom the office space was hired.


Poor management of hired office space by the CAO coupled with the inability of the designated defence users to shift to the said premises for a period of more than four years resulted in wasteful expenditure of ₹44.26 crore (March 2023) on account of rent of the unutilised space as well as renovation works carried out therein.


Raising of Porter Companies in Eastern Command: Ministry of Defence sanctioned (June 2019) raising of nine Porter Companies (Coys) in the area of responsibility (AoR) under the Headquarters Eastern Command (HQ EC) for the years 2019-20 and 2020-21 at a cost of ₹180.85 crore and for the year 2021-22, at a cost of ₹93.78 crore.


The assessment of requirement of porters carried out by the two Division HQ (HQ ‘C1’ Division and HQ ‘C2’ Division), under HQ ‘C’ Corps, was not commensurate with their respective five- year Roll-on Plans (RoPs). The Engineer Task Forces (ETFs) under these Divisions were marginally short of manpower for the years 2019-20 and 2020-21 and had surplus manpower during the financial year 2021-22 for the execution of operational works as per the RoPs. However, the Ministry, on the basis of projection of requirements, sanctioned eight Porter Coys for the period from 2019-20 to 2021-22 comprising 600 porters in each Porter Coy for HQ ‘C’ Corps.


The works projected by three Corps HQ for obtaining sanction for raising of Porter Coys were in excess of works actually executed during 2019-20 to 2021-22 to the extent of 41 to 499 per cent. Two Corps HQ (HQ ‘A’ Corps and HQ ‘C’ Corps) projected 8,635 porters, involving an expenditure amounting to ₹112.93 crore, in excess of the requirement based on the volume of works executed during the years 2019-20 to 2021-22.


The sanction for raising of Porter Coys for the years 2020-21 and 2021-22 was issued in time by the Ministry. However, HQ ‘B’ Corps and HQ ‘C’ Corps raised Porter Coys with a delay of up to three months. The delay in the raising of Porter Coys contributed to fall in the strength of porters in seven out of eight selected Porter Coys due to onset of winter.
Out of total 12,000 porters hired under the Porter Coys raised between 2019-20 and 2021-22, Corps HQ allotted 11,297 porters to ETFs/Engineer Regiments. Division HQ further allotted only 7,938 porters to ETFs/Engineer Regiments. As such, 3,359 porters were deployed in units other than Engineer Regiments. Out of 7,938 porters deployed, the utilisation certificates rendered by the Engineer Regiments were only in respect of 4,634 porters.

There was an overpayment of ₹2.53 crore to Porters due to payment of salary on a daily basis instead of on monthly basis and payment at enhanced rates of basic pay and dearness allowance to Porters deployed as mates. Besides, ₹1.21 crore were also paid on account of high altitude allowance (HAA) to those porters who were not deployed in high altitude areas. There was delay in disbursement of salary to porters ranging from one to five months.
There was shortfall of 97and 80 per cent in respect of HQ ‘A’ Corps and HQ ‘B’ Corps in construction of Permanent Defences (PDs) against those projected in the five-year RoP (2018-23), despite sanctioning of Porter Coys during 2019-20 to 2021-22. Audit found that in respect of two Corps HQ, no Board of Officers (BOO) was held for handing over the assets to the users during the years 2020-21 and 2021-22 (HQ ‘A’ Corps), and 2021-22 (HQ ‘C’ Corps). In HQ ‘C’ Corps (HQ ‘C2’ Div.) for the years 2019-20 and 2020-21, Numerical Asset Register (NAR) was not updated and there was a mismatch between the number of PDs, shelters and storage accommodation constructed, and those reflected in the NAR.


Court of Inquiry in Indian Army:


There were persistent delays in finalisation of the CoI proceedings in Indian Army. Out of 95 cases involving financial loss in the three Army Commands (Central Command, Eastern Command and Western Command), stipulated timeline for assembly and completion of CoI was met only in 46 and 25 cases respectively. In 11 cases, time taken in completion of CoI was more than two years and even up to 11 years. In 10 CoIs related to fire incidents where the Command HQs were authorised to convene a CoI, the convening order was issued by an authority lower than the Command HQs. The terms of reference (ToR) which lay down the scope of investigation for a CoI did not have specific mention of fixation of responsibility and apportioning of blame/loss in 29 cases. Further, in 28 out of these 29 cases, there was no mention of the relevant Army Rules, Orders, Instructions, etc., and in 13 of these 29 cases, no mention was made of assessing the extent of loss and damage to life/property.


In 95 cases, CoI assessed financial loss of ₹50.76 crore. The financial losses of ₹7.12 crore were regularised in respect of 43 cases (April 2022). However, in 52 cases involving financial loss of 43.64 crore, the information relating to regularisation of loss by Competent Financial Authority was not available. In 57 out of 95 cases, the required documents relating to intimation of details of loss to accounting authorities, that is, Controllers of Defence Accounts (CsDA), were not available in the documents furnished. As such, Audit was unable to ascertain whether the loss was reported to CsDA either initially or finally after investigation. In 20 out of 38 remaining cases, where the Commands/Units furnished details of financial losses to the concerned CsDA after completion of CoI, the time taken in reporting of losses to CsDA ranged between three months and more than two years.


Hiring of accommodation due to inordinate delay in construction of warehouse: Lackadaisical approach on the part of authorities of the Canteen Stores Department (CSD) and the Military Engineer Services (MES) in processing the case for construction of a warehouse for CSD Area Depot Chennai, first initiated in February 2011, coupled with delay on

the part of Ministry of Defence (Ministry) in according sanction, resulted in inordinate delay of 393 weeks in pre-administrative approval planning. The overall time taken in processing the proposal and according the sanction was 441 weeks as against the stipulated time frame of 48 weeks. There were further delays even after the work was sanctioned in July 2019 due to late release of funds by the Ministry. The contract was finally concluded in December 2022 and the work is scheduled to be completed by November 2024. CSD has paid ₹17.43 crore as rent from October 2018 to December 2022 towards hiring of a warehouse for the CSD Area Depot Chennai.


Unwarranted expenditure due to delay in termination of Bandwidth services by the Canteen Stores Department: The VSAT connectivity required for functioning of the Integrated Canteen Stores Department (ICSD) system, was unsatisfactory since October 2009 which was well known to the CSD. The letter for termination of VSAT services was issued only in July 2014, though the payments towards VSAT connections were stopped by the CSD since October 2013. Meanwhile, as the contract remained in force from October 2013 to June 2014, the firm raised invoices for VSAT Services indicating that 18 per cent interest would be charged on delayed payment, which was not responded to by the CSD.


The firm filed (July 2017) a suit in the Delhi High Court which appointed (August 2018) a Sole Arbitrator for the case. The Arbitral award was pronounced (February 2020) in favour of the claimant and CSD had to incur an unwarranted expenditure of ₹1.85 crore towards arbitration award.


Avoidable extra expenditure due to acceptance of unreasonable rate: Integrated Headquarters of Ministry of Defence (IHQ) (Army) floated (January 2018) an open tender enquiry for the supply of 8,831 pieces of ‘S’ item. Only M/s Ashok Leyland, the Original Equipment Manufacturer (OEM), qualified in the technical bids. OEM quoted (May 2018) a base price of
₹4,500 (exclusive of tax). Director General of Ordnance Services (DGOS) at the Army HQ placed (August 2018) the Supply Order (SO) after a gap of three months as against the prescribed four weeks.


In the interregnum, Central Ordnance Depot (COD), Dehu Road, separately placed a SO (July 2018) for procurement of 1,617 pieces of the ibid item at a base price of ₹8,400 (exclusive of tax) through a limited tender issued (June 2018) to 14 shortlisted suppliers (excluding the OEM). This rate was much higher than the Army HQ determined price of May 2018 by ₹3,900 per piece (excluding tax). While assessing the reasonableness of the cost, COD compared the rates with its earlier procurement (February 2016) from the same vendor which was ₹8,400 (excluding tax) instead of comparing it with its last procurement (September 2017) from OEM which was ₹4,551 (excluding tax).


This resulted in COD, Dehu Road procuring the item in July 2018 at a price higher than the price at which Army HQ had finalized contract for the same item in May 2018, thus incurring an avoidable extra expenditure of ₹80.72 lakh inclusive of tax.

Management of Water Supply by Military Engineer Services: Military Engineer Services (MES) is responsible for the erection, operation and maintenance of all defence services installations for the supply of water to users in its assigned area of responsibility viz. Military stations, Cantonment Boards and other Defence Installations.


Audit examination of records for the period from 2018-19 to 2020-21 at 20 selected Garrison Engineers (GEs), under six commands, regarding management and augmentation of water supply revealed that in 15 out of 20 GEs selected, water supplied to the users was less than that authorised. The less supply of water in the said 15 GEs ranged from 10.13 per cent to 62.97 per cent of the authorised quantity.


To reduce the gap between the demand and supply of water in their respective service areas, 13 GEs had signed Memoranda of Understanding/agreements with outside agencies (water supply utilities). Analysis of the information on actual water supply by the contracted agencies revealed that 12 out of the 13 GEs were receiving less than the agreed upon quantity of water from these agencies.


Engineer-in-Chief’s Branch had issued (November 2018) instructions to implement the automation of process supervisory management of water supply system within the MES. This had not been implemented by16 GEs.


It was further observed that 14,940.33 lakh gallons of water were lost due to leakage in the period from 2018-19 to 2020-21. The total loss on account of leakage of water calculated on the basis of ‘All-in-Cost’ worked out to ₹11.53 crore.


Out of 10 projects related to augmentation of water supply under Annual Major Works Programme (AMWP), which were selected for detailed audit, only four projects were completed whereas one project had yet not started and five projects, which had started, were still to be completed.


Significant lapses such as non-compliance with applicable standards of the Bureau of Indian Standards (BIS) for quality of drinking water, non-cleaning of Overhead Tanks/Reservoirs at the prescribed frequency, and non-functional equipment for water decontamination were noticed.


There was less allotment of funds against demand in the water supply maintenance head during the years 2018-19 to 2020-21 in 18 of the selected GEs ranging from 13.80 per cent to 47.67 per cent.


Irregular payment of Electricity Duty by MES formations due to failure to install separate meters for domestic and non-domestic consumption of electricity: Military Engineer Service is responsible for the management of electric supply in all the military stations/cantonment areas in the country, for which it receives bulk electric supply from the State Electricity Boards or companies (supplying agencies). Before payment to the supply agency for bulk supply of electricity as per the applicable charges, Garrison Engineer (GE) concerned is required to enforce pre-checks on the bills. Audit observed that despite the assurance given by the Ministry, GE, Mhow and GE, Jabalpur paid Electricity Duty (ED) amounting to ₹4.81 crore

(March 2022) on non-domestic (non-dutiable) consumption of electricity by Defence Establishments to electricity supplying agencies. Non-recovery of allied electricity charges on domestic supply by Garrison Engineer (Faridkot) amounting to ₹1.28 crore: An amount of ₹ 1.28 crore remained unrecovered for the period of 2018-19 to 2020-21 from domestic users residing in Faridkot military station due to failure of Garrison Engineer Faridkot to ensure recovery of electricity charges as per stipulated regulations.


Avoidable expenditure of ₹3.20 crore on account of not following the IRC specification in road markings: Chief Engineer (Project) Chetak failed to incorporate IRC standards in the 38 contracts related to road resurfacing concluded during the period 2019-20 to 2021-22 and provide edge line marking of width 150mm instead 100 mm resulting in avoidable expenditure of ₹ 3.20 crore on account of laying of thermoplastic paint on the excess area.


Sanctioning similar nature of works under different code heads: Defence Research & Development Laboratory (DRDL), Hyderabad sanctioned ₹4.10 crore for procurement of a Closed Circuit Television (CCTV) surveillance system for the entire perimeter wall of the lab exercising the financial powers delegated to the Director under Sl. No. 2.2 of Delegation of Financial Powers, 2019 (DFP). The said delegation is applicable only for procurement of scientific equipment and material for labs/workshops. Intent of DFP is to consider only that equipment as scientific equipment which may be required in connection with the scientific research and development work pertaining to the laboratory. As such, installation of CCTV surveillance system should come under the ambit of ‘Works’ and not ‘Procurement of scientific equipment’. Incidentally, based on the requirement of CCTV surveillance cameras projected by another laboratory, Director, Civil Works & Estates, Head of the Construction Wing of Defence Research and Development Organisation (DRDO), had accorded required sanction under Sl. No. 4.1 of DFP, which is applicable for ‘Works’.


Avoidable expenditure of ₹2.78 crore: Injudicious selection of location for setting up of the Defence Research & Development Organisation Young Scientist Laboratory – Asymmetric Warfare Technologies (DYSL-AT) at Kolkata resulted in relocation of the Laboratory within one year and four months to Hyderabad. During this period, an expenditure of ₹2.78 crore was incurred on civil works/rent at two different sites towards establishment of DYSL-AT at Kolkata which was avoidable.

Continue Reading

India News

Mani Shankar Aiyar’s remarks on Hindutva spark political backlash from BJP

Congress leader Mani Shankar Aiyar’s comments on Hindutva at a Kolkata debate have triggered sharp reactions from the BJP, escalating the Hinduism versus Hindutva debate.

Published

on

manishankar aiyer

Veteran Congress leader Mani Shankar Aiyar has triggered a political controversy after describing Hindutva as “Hinduism in paranoia” during a public debate in Kolkata, prompting a strong rebuttal from leaders of the Bharatiya Janata Party (BJP).

Aiyar made the remarks at a discussion titled “Hinduism needs protection from Hindutva”, organised by the Calcutta Debating Circle at the Calcutta Club on Sunday. Several political leaders, legal experts, historians and journalists participated in the debate.

Aiyar draws distinction between Hinduism and Hindutva

Speaking at the event, Aiyar argued that Hinduism and Hindutva are fundamentally different, describing Hinduism as a spiritual and civilisational faith, while calling Hindutva a political ideology that emerged in the early 20th century.

“Hindutva is Hinduism in paranoia. It asks 80 per cent Hindus to feel threatened by 14 per cent Muslims,” Aiyar said, adding that Hinduism had survived and flourished for thousands of years without the need for what he described as political protection.

He referred to incidents involving attacks by vigilante groups and criticised actions against individuals over religious practices, beef consumption and participation in Christmas celebrations. Aiyar also cited writings of Vinayak Damodar Savarkar, contrasting them with the teachings of Mahatma Gandhi and Swami Vivekananda, whom he described as proponents of non-violence and inclusivity.

According to Aiyar, “There is no way Gandhi’s or Vivekananda’s Hinduism can be protected or promoted by Savarkar’s Hindutva.”

BJP leaders push back strongly

Aiyar’s comments drew an immediate response from BJP leaders present at the debate and later from party spokespersons.

BJP MP Sudhanshu Trivedi questioned the framing of the debate itself, arguing that the term “Hindutva” refers to “Hindu tattva” or the essence of Hindu philosophy. He said that associating Hinduism with the suffix “ism” was misleading and dismissive of India’s indigenous traditions.

“When you cherish Hinduism, it is called Hindutva,” Trivedi said, rejecting the distinction drawn by Aiyar.

BJP spokesperson Shehzad Poonawalla accused Aiyar of repeatedly making remarks that, according to him, insult Sanatan Dharma. He claimed that the comments echoed the Congress party’s broader stance on Hindutva.

Poonawalla also referred to past statements by Congress leaders and said that Hindutva has been defined by the Supreme Court as a “way of life.” He accused the party of attempting to portray Hindutva as violent and divisive.

Political debate intensifies

The exchange has added to the ongoing political debate over the relationship between Hinduism and Hindutva, a subject that has remained contentious in Indian politics. While Aiyar defended his views as ideological and historical critique, BJP leaders framed the remarks as an attack on religious identity.

Continue Reading

India News

TVK chief Vijay to appear before CBI in Karur stampede probe

TVK leader Vijay will appear before the CBI in Delhi as part of the probe into the Karur stampede that claimed 41 lives during a political rally in 2024.

Published

on

Tamilaga Vettri Kazhagam (TVK) chief and actor Vijay is set to appear before the Central Bureau of Investigation (CBI) in Delhi on Monday in connection with the Karur stampede case that claimed 41 lives. The incident occurred on September 27 last year during a massive political rally addressed by Vijay, making it one of the deadliest crowd-related tragedies in Tamil Nadu’s recent political history.

Supreme Court handed probe to CBI

The investigation into the stampede has undergone multiple legal changes. Initially, the Madras High Court had constituted a Special Investigation Team (SIT) to probe the incident. However, the Supreme Court later transferred the case to the CBI, directing that the investigation be monitored by a panel headed by a retired Supreme Court judge.

The apex court also set aside a one-member commission earlier appointed by the Tamil Nadu government, observing that the matter required a more independent and credible inquiry. Notably, TVK itself had sought an independent probe into the tragedy.

A senior party source told media that Vijay would cooperate fully with the investigation and expressed hope that the truth would emerge through the CBI inquiry.

Police and Vijay trade blame

Following the stampede, the Tamil Nadu Police had attributed the chaos to Vijay’s alleged delay in reaching the venue, claiming the prolonged wait led to an uncontrollable surge of the crowd. Police officials had also pointed to inadequate arrangements such as food, drinking water and toilet facilities, stating that the situation worsened as the crowd grew restless.

Vijay rejected these allegations, calling them a conspiracy by the ruling DMK, a charge the party has denied. He, in turn, blamed the police for poor crowd management and failure to clear bottlenecks on approach roads leading to the rally venue.

Film certification issue adds political edge

Vijay’s appearance before the CBI comes amid a separate controversy over the delay in certification of his film Jana Nayagan, which was originally slated for release ahead of Pongal. While a single judge of the Madras High Court had directed the Central Board of Film Certification (CBFC) to grant certification, a division bench later stayed the order and adjourned the matter to January 21. Neither Vijay nor TVK has officially commented on the issue.

Opposition leaders, including those from the Congress, have alleged that central agencies are being used to exert pressure on TVK ahead of the Tamil Nadu Assembly elections due in a few months. Chief Minister MK Stalin recently remarked that the CBFC had “joined the list of central agencies being used as weapons by the Union government.”

The BJP has rejected these allegations. The party has also denied speculation that it is indirectly aiding TVK to split anti-DMK votes following its renewed alliance with the AIADMK.

Political stakes ahead of elections

Vijay has repeatedly described the upcoming Assembly election as a direct contest between the ruling DMK and TVK, referring to the DMK as his “political enemy” and the BJP as his “ideological enemy.”

Responding to questions on whether the ongoing CBI probe could make the party vulnerable to political pressure, a senior TVK leader said the party had faith in the investigation and would approach the courts if any undue pressure was applied.

Continue Reading

India News

Drunk speeding Audi crushes pedestrians in Jaipur, one killed and 15 injured

A late-night crash involving a drunk speeding Audi in Jaipur left one pedestrian dead and at least 15 others injured after the car ran over roadside vendors and pedestrians.

Published

on

car accident

One person was killed and at least 15 others were injured after a speeding Audi car, allegedly driven by drunk occupants, ran over pedestrians and roadside vendors in Rajasthan’s Jaipur late Friday night.

According to the police, the luxury car lost control and first hit a road divider before ploughing into food carts and roadside stalls over a stretch of nearly 30 metres. The vehicle eventually crashed into a tree and came to a halt, damaging several parked vehicles along the way.

Visuals from the scene showed shattered food carts scattered across the road, while the Audi was left completely mangled due to the impact.

A total of 16 people were hit in the incident and were rushed to a nearby hospital. Four of the injured were reported to be in critical condition and were later referred to Sawai Man Singh (SMS) Hospital for advanced treatment.

One of the injured, identified as Ramesh Bairwa, a resident of Bhilwara, succumbed to his injuries during treatment.

Police officials said that four people were inside the car at the time of the crash, and all of them were allegedly under the influence of alcohol. While one person has been arrested, three others fled the spot after the incident.

The driver of the Audi has been identified as Dinesh Ranwan, a resident of Churu district in Rajasthan. The vehicle has been seized, and a search is underway to trace the remaining accused.

Rajasthan Chief Minister Bhajanlal Sharma expressed grief over the incident and instructed officials to ensure proper medical care for the injured. Deputy Chief Minister Premchand Bairwa and Health Minister Gajendra Singh Khimsar visited the hospital to enquire about the condition of those injured.

Continue Reading

Trending

© Copyright 2022 APNLIVE.com